Storm Pipe Repair in Statesville Set for May 15 on Hartness Road

by | May 15, 2025

A storm pipe repair is scheduled for Thursday, May 15, 2025, near 735 Hartness Road in Statesville. Work will begin at 9:30 a.m. and is expected to conclude by 4:00 p.m. During this period, traffic will be reduced to one-way with flaggers guiding vehicles through the work zone.

The repair is prompted by signs of subsidence in the roadway, suggesting potential underground voids or damage to the storm pipe, which could affect roadway stability and public safety.

Contractors will use Deep Soil Injections with polyurethane foam to strengthen the area. This method helps fill voids, improve soil strength, reduce erosion, and seal cracks in the storm system. The injections will follow a pattern of about seven points per side, starting on the north side of the street and moving southward.

Motorists are advised to anticipate minor delays and to drive carefully through the area during the scheduled work.